Undocking the Anthem of the Seas is advanced on Friday afternoon

Undocking the Anthem of the Seas is advanced on Friday afternoon

Back to overview
Based on the latest weather forecasts, undocking the Anthem of the Seas is the February 20, 2015 brought forward to Freitagnachmitttag around 15:00 clock.
This is due, among other things, the wind sensitivity of the two floating parts of the Norwegian Escape, which lie at the time of Ausdockens the Anthem of the Seas in Werfthafen and moved.
Also, the placement of the chimney, organizing the required tests and raise the Northstar is brought forward to Saturday.
Delays and temporal changes in the undocking possible due to weather conditions.

In order to facilitate the application of the Anthem of the Seas at the pier, which is currently located at the fitting first floating part of the Norwegian Escape is hauled. The second part of swimming, which is currently in the dock II shipyard is undocked before the Anthem of the Seas and then also within the shipyard harbor. After undocking the Anthem of the Seas, the two floating parts of the Norwegian Escape, which will be completed in the fall of 2015 maneuvering for the further construction in the building dock II free.
For this purpose, it is necessary to cross the sea lock on 19 February from about 7:30 to about 16:00 clock clock and on February 20 from 12:00 clock until February 21 to about 15: back to 00 clock . Lock On Sunday, February 22, it is because of the Dockschleusung the tractor to another locking in from 12:00 clock bis 19:00 clock. All times subject to weather conditions