Friday 6 March 2015

Set the first block of the "Ovation of the Seas" into the Dock

Set the first block of the "Ovation of the Seas" into the Dock

In building dock II Meyer Werft in Papenburg now the first block for the cruise ship ovation of the Seas was placed on the Pallungen. Adam Goldstein, Royal Caribbean International, together with Bernard Meyer, put the lucky penny on the Pallungen before the 800-ton crane deposed the block of the new ship.
This block is one of the 74 blocks of the new luxury liner and has a weight of 740 tons. This officially keel laying, construction begins on the Ovation of the Seas, which counts with a survey of 168,600 gross tonnage of the 5 largest cruise ships in the world.
The first flame cut steel for the ovation of the Seas took place in September 2014. Meyer Werft in laser center. The ship will be delivered in April 2016.
The Anthem of the Seas, which is currently on Equipment pier of the Meyer Werft is completed and the next week Papenburg leaves towards the North Sea, the second ship in a series of three ships being built for Royal Caribbean International at Meyer Werft.
Photo 2:. Vl Lambert Kruse (Managing Director Meyer Werft) Jarmo Laakso (Project Manager Royal Caribbean) Adam Goldstein (CEO, Royal Caribbean International) Bernard Meyer (Managing Director Meyer Werft), Dr. Jan Meyer (CEO Meyer Werft), Mika Heiskanen (Project Manager Royal Caribbean), Carsten Pengel (Project Meyer Werft) Claus Andersen (-Anthem captain of the Seas - Royal Caribbean)